We've all run across performance products that are claimed to make tremendous power gains—sometimes too tremendous to believe. However, you can believe what you hear in the case of the diesel PowerPack kits from Gale Banks Engineering, specifically the kits for the Dodge Cummins turbodiesel engines. A true 114 percent increase in horsepower and 81 percent more torque are possible with simple-to-install bolt-on parts.

We couldn't resist the prospect of waking the sleeping giant under the hood of a 1997 Dodge turbodiesel, so we followed the installation of a complete PowerPack system at Gale Banks Engineering. At the end, we did a dyno-test thrash to see if we could duplicate the numbers.

As it turns out, the PowerPack system didn't just wake the sleeping giant, it made him downright mad. We suspected the Cummins turbodiesel engine was a good candidate to make serious horsepower (a version of the engine found in Dodge trucks is used to propel some 18-wheelers), and even though our test truck didn't exactly duplicate the Banks claims for reasons we'll explain later in this article, the power a few basic bolt-on parts yielded is impressive. Beyond the power gains, the quality and fit of the components are among the best we've seen, and the detailed instructions were written with the do-it-yourselfer in mind. Find out what it takes to install a Banks PowerPack kit in the photos and captions, and then check out the acceleration and dyno-test results.

  • P50860 Image Large
    The Banks PowerPack system consists of an air filter, an intake manifold, a revised turbo housing, an exhaust system, a fuel-calibration plate, and gauges--not a lot of parts when you consider the gains. There's no magic to the parts; they're simply engineered to work well together as a system. Plus, thanks to the detailed instructions (which include plenty of diagrams), a shadetree mechanic with an average-sized toolbox can install the system over a weekend.
    P50860 Image Large
    The Banks PowerPack system consists of an air filter, an intake manifold, a revised turbo
  • P50861 Image Large
    One of the key components to the PowerPack system is the Twin Ram intake manifold. Instead of a single inlet to feed all the cylinders, the Twin Ram splits the intake, providing better air and boost distribution to the engine. After looking at the original intake, it's hard to see why the engineers didn't do it this way from the factory.
    P50861 Image Large
    One of the key components to the PowerPack system is the Twin Ram intake manifold. Instead
  • P50862 Image Large
    The first step of the installation involves removing the original muffler and tailpipe assembly. Although the tailpipe appears large (about 3 1/2 inches) at the end, it necks down over the rearend and is a restriction. The Banks tailpipe is 3 1/2 inches throughout. The stock system is clamped together, but it's necessary to heat the slip joints to ease removal without damaging the rest of the system. The factory clamps and hangers are reused with the new muffler assembly, and no cutting or welding is required. The catalytic converter has a tab that indexes a notch on the muffler, taking the guesswork out of proper positioning.
    P50862 Image Large
    The first step of the installation involves removing the original muffler and tailpipe ass
  • P50863 Image Large
    Disconnect the intake and exhaust plumbing from the turbo housing, then carefully loosen the mounting bolts and remove the turbo from the exhaust manifold. Place the turbo assembly in a vise. It's necessary to separate the exhaust portion of the assembly, so scribe a mark between the two pieces to ensure the new Banks piece can be positioned the same way on the turbo. Unbolt the wastegate assembly per the instructions, loosen the bolts connecting the two pieces, and carefully separate them. It may be necessary to lightly tap the connection to persuade the parts to separate, and be sure to remove any residual rust before installing the new turbine housing.
    P50863 Image Large
    Disconnect the intake and exhaust plumbing from the turbo housing, then carefully loosen t
  • P50864 Image Large
    There is not much visible difference between the Banks Quick Turbo housing (left) and the original. However, the revised one allows the turbo to spool up quicker, providing more power at a lower rpm. Transfer the appropriate parts from the original to the new housing, and note how the original was positioned so that you know how to install the new housing.
    P50864 Image Large
    There is not much visible difference between the Banks Quick Turbo housing (left) and the
  • P50865 Image Large
    Before reinstalling the turbo housing, drill and tap a hole in the rear outlet of the exhaust manifold. Stuff a rag in the exhaust port before drilling to catch the metal particles, and thoroughly clean the port with a vacuum to ensure these particles don't damage the rest of the system. This hole will be the location for the pyrometer sending unit, which is included with the PowerPack kit.
    P50865 Image Large
    Before reinstalling the turbo housing, drill and tap a hole in the rear outlet of the exha
  • P50866 Image Large
    Remove the intake-manifold cover and the inlet port (or upper intake). Start loosening the fuel lines that run from the injector pump to the injectors on the other side of the engine with a line wrench if one is available. Use caution when lifting away these steel lines, and do not attempt to bend them--they're easy to damage and expensive to replace. The fuel lines can be removed as an assembly. Use the plastic caps supplied with the kit to cover the outlets on the injector pump. Any debris that enters the fuel system can have disastrous effects on the engine.
    P50866 Image Large
    Remove the intake-manifold cover and the inlet port (or upper intake). Start loosening the
  • P50867 Image Large
    The amount of fuel that flows to the engine is controlled by a fuel-calibration cam located under a cover toward the rear of the pump (shown here with the cover already off). This is perhaps the trickiest part of the installation, so it's important to follow the instructions exactly, including using scribe lines to mark the position of the cover so it can be reinstalled in exactly the same spot. Once the appropriate brackets and lines are out of the way, you'll notice the factory-installed tamperproof screw, which has no head, in the upper lefthand corner. Use a chisel to make a slot in the screw suitable for a flatblade screwdriver. All of the cam-cover screws will be extremely tight, so investing in an inexpensive impact screwdriver may be helpful.
    P50867 Image Large
    The amount of fuel that flows to the engine is controlled by a fuel-calibration cam locate
  • P50868 Image Large
    Don't touch the fuel-calibration plate yet! Scribe two lines across the pump body to mark the exact position of the stock cam plate, then install the guide template supplied with the kit and butt the forward edge of the template (closest to the front of the engine) against the stock cam. Carefully take out the stock cam plate without moving the template and replace it with the one supplied in the kit, making sure it's in the same place as the original. Once the new cam plate is secure, remove the template and reinstall the cam cover.
    P50868 Image Large
    Don't touch the fuel-calibration plate yet! Scribe two lines across the pump body to mark
  • P50869 Image Large
    With the injector-pump work done, move on to the rest of the intake swap. Remove the lower intake (don't forget to disconnect the wires for the heating elements), and clean the gasket surface. Install the new lower intake on the head, using a dab of Loctite on each of the retaining bolts. Install the rest of the hardware, including the air-temperature sensor and the fuel-filter bracketry. You can now separate the fuel-injector lines and install them on the engine, using the supplied clamp assemblies.
    P50869 Image Large
    With the injector-pump work done, move on to the rest of the intake swap. Remove the lower
  • P50870 Image Large
    Instead of glow plugs in each cylinder, the Cummins engine uses two stacked heating elements located in the intake. These heating elements must be taken out of the original intake and installed in the heater housings of the new intake. It may be necessary to bend the leads slightly, but be careful not to damage them. Pay close attention to the order of the hardware, including the insulators and power-supply studs. The elements are separated from one another with the new intake, (one for each port) but there is no negative effect on starting capability.
    P50870 Image Large
    Instead of glow plugs in each cylinder, the Cummins engine uses two stacked heating elemen
  • P50871 Image Large
    Install the heater housings on the lower intake followed by the upper intake, using the supplied gaskets. Again, pay close attention to the order of the fasteners and their washers. They're designed to withstand the vibrations of the engine without loosening. The grounding straps for the heating elements must be carefully bent over the intake once it's in place. On California models equipped with an EGR valve, install the metal gasket in the upper intake.
    P50871 Image Large
    Install the heater housings on the lower intake followed by the upper intake, using the su
  • P50872 Image Large
    Since the heating elements are now in a different location, it's necessary to separate the two power leads for the elements from the harness near the injector pump. No cutting is required beyond removing some electrical tape, and the harness can be left with its plastic loom intact. Use some electrical tape to keep the leads from separating from the harness further, and carefully route and connect them to the heating elements.
    P50872 Image Large
    Since the heating elements are now in a different location, it's necessary to separate the
  • P50873 Image Large
    Now that the major work is out of the way, assemble the gauge cluster and place it on the dash. The cluster comes in and even has a texture to match the rest of the dash. Carefully route the tubing and wires for the boost gauge and pyrometer using the suggestions found in the installation manual. The lighting for the gauges should be connected to a headlight circuit, which can easily be found on the nearby fuse panel, and the ground wire can be attached to any solid metal bracket under the dash.
    P50873 Image Large
    Now that the major work is out of the way, assemble the gauge cluster and place it on the
  • P50874 Image Large
    Reinstall any of the remaining parts and hoses that were taken out during the installation, and double-check your work to make sure nothing was missed. The final step is to purge the fuel lines of any trapped air. If the engine won't start or runs poorly, loosen the banjo fitting above the fuel filter and use the push-button primer to free any air trapped in the main fuel line. If the engine still runs poorly or not at all, loosen the steel fuel lines one at a time and crank the engine until it appears that only fuel is escaping the fittings, then quickly tighten them. Use extreme caution during this procedure to prevent the high pressure fuel from puncturing your skin or spraying over a hot engine.
    P50874 Image Large
    Reinstall any of the remaining parts and hoses that were taken out during the installation
Enjoyed this Post? Subscribe to our RSS Feed, or use your favorite social media to recommend us to friends and colleagues!

*Please enter your username

*Please enter your password

*Please enter your comments
Comments:
Not Registered?Signup Here
(1024 character limit)
4Wheel & Off-Road